Hwange 150MW power plant construction begins Work on new Hwange Power Station shows progress done on the ground to date

Fairness Moyana in Hwange

ZIMBABWE Zinghxon Electrical Energy (ZZEE) has begun construction of a 150MW thermal power station in Hwange that is set to boost power generation and stimulate economic growth in the region.

The company, which is a joint venture between Zimbabwe and China, is already running a coking plant in the district. The project began in February this year and is set to be completed in three years’ time. 

ZZEE managing director, Mr Jun Wen Wang, said the project was being rolled out in two phases with the first stage involving the construction of a 2x25MW thermal power station while the second 2x50MW unit will be added later.

“We came here to develop Zimbabwe’s electricity economy. Six years ago this company came to Zimbabwe to invest and we have since started operations. 

“What we are constructing is a 2x25MW thermal power station. After that, looking at the company’s future, we are planning to build, in the second phase, another 2x50MW unit,” said Mr Wang.

“We started constructing the power plant in February this year and according to our plan we will be through0 in three years. 

“However, we are trying our best to finish it within two years instead. The foundation for the two boilers, which is now in the fourth month, is almost done.”

He said once construction of the power station was complete, 300 000 tonnes of coal will be required to run the plant and this will be supplied by Hwange Colliery Company and Makomo Resources.

“At 50MW we will require 300 000t per month and will engage Makomo and Hwange Colliery to supply us. 

“We are already working with the two mining companies who are currently supplying us at our coking plant. Also this project will employ 160 people, most of them being locals.”

Mr Wang said they had since expanded their coking plant at one of their companies in Lukosi with production of coke having increased significantly.

“This year we expanded our coke plant and at the same time we built another coke plant in Hwange district. 

“The second plant is already running that is why we have increased the raw material to about 12 000t per month to run both plants but the suppliers are not meeting our required targets,” he said. 

“The expansion of the coking plant will double our output. We are currently producing about 8 000t of coke per month. 

“We are getting our coal from Makomo and HCCL but they are not meeting the required target of what we want.”

The company, Zimbabwe Zinghxon Coking Company (ZZCC), exports 80 percent of its coke to the Democratic Republic of Congo (DRC) while Zambia gets 10 percent. 

Botswana and the other neighbouring countries share the remaining 10 percent. According to the company, plans are at an advanced stage to build another chrome smelting plant and also resume construction of their suspended cement plant in Masvingo. 

During a recent tour of coal mining companies, Mines and Mining Development Minister, Winston Chitando, said Government would support the project as it was one of the key investments in the sector.

You Might Also Like

Comments